| Concrete 145,000 cubic metres of reinforced concrete were used in the bridge substructure and approach viaducts. |
|||||||||||||||||||||||||||||||||||
|
Snow Clearance
Dartford River Crossing has contingencies for keeping the traffic flowing in all weather conditions including heavy snow and ice. |
|||||||||||||||||||||||||||||||||||
| Air Change Four ventilation buildings are situated directly above the tunnels. Axial flow fans replace polluted air which is extracted through large chimneys |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
|
Total Bridge Length
The total length of the bridge including the approach viaducts is 2.872 kilometres. |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
|
Replacing the Road Deck
The east tunnel road deck was replaced during the nights in prefabricated 45 tonne sections. The tunnel was open to traffic as normal during daytimes throughout duration of the works. |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||
| Patrol Vehicles Each patrol vehicle travels at an average of 40,000 miles per annum within the concession area. |
|||||||||||||||||||||||||||||||||||
|
Main Span
The main span is 450 metres, with the road deck 65 metres above the river providing at least 57.5 metres clearance over the width of the navigational channel. |
|||||||||||||||||||||||||||||||||||
|
For a bigger and more detailed picture selection why not go to the Photo Gallery .
|
|||||||||||||||||||||||||||||||||||
|
Pylons
84 metre high steel pylons are located above 53 metre high concrete piers giving the bridge a total height of 137 metres. From these the road deck is suspended by cables. |
|||||||||||||||||||||||||||||||||||
| Tunnel Cleaning The tunnels undergo a regular programme of water jet spray cleaning and have to be washed weekly during the winter months. |
|||||||||||||||||||||||||||||||||||
| <back | |||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||